Case Study
Public Improvement for I-90/Oriole Bridge Replacement
Location:
I-90 and Oriole, IL
Summary:
- 16 inch steel relocation for bridge replacement
- Reroute gas main on north and south side of interstate
Project Challenges:
- Constrained timeline
- Working alongside interstate with extremely heavy vehicle traffic
- Steep slopes with difficult ingress/egress for project
- Required schedule coordination with bridge contractor
Creative Solutions:
- Developed alternate construction plan to shorten required construction timeframe
- Coordinated work on both sides of interstate simultaneously to meet required schedule
Results:
- Project completed ahead of schedule
- Project complete without incident